Grid Prep Start free

3.a · Emergency Preparedness · free sample

Same-Day and Next-Day Planning

3.a Same-Day and Next-Day Planning is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 4 scored questions on RC, 4 on BT, 4 on TO and 4 on BI. It carries the same weight on all four exams. Grid Prep has 36 questions on it. In the bank, they most often cite IRO-017-1, TOP-002-4 and EOP-011-4. Two are free below.

Free sample: 2 of 36

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

NERC Reliability Standard IRO-014-3 requires each Reliability Coordinator's coordination documents with adjacent Reliability Coordinator Areas to cover the exchange of

  1. A. hourly energy billing statements
  2. B. generator fuel supply contract terms
  3. C. planned and unplanned outage information
  4. D. retail customer metering and billing records
Show the answer

Answer C planned and unplanned outage information

Part 1.4 of Requirement R1 lists the exchange of information including planned and unplanned outage information to support Operational Planning Analyses and Real-time Assessments. The other items are commercial or retail data that have no bearing on an adjacent Reliability Coordinator's studies.

Reference: IRO-014-3 R1 Part 1.4

Question 2 · Analysis

A Reliability Coordinator issues an Operating Instruction to postpone a Transmission outage, but the crew is already inside the equipment and the line cannot be safely returned. What must the Transmission Operator do?

  1. A. Return the line to service anyway, since the instruction is mandatory
  2. B. Refer the instruction to its Planning Coordinator for a ruling
  3. C. Log the conflict and raise it at the next shift turnover
  4. D. Inform its Reliability Coordinator that it cannot perform the instruction
Show the answer

Answer D Inform its Reliability Coordinator that it cannot perform the instruction

Requirement R2 requires compliance with a Reliability Coordinator's Operating Instruction unless it cannot be physically implemented or would violate safety, equipment, regulatory or statutory requirements, and Requirement R3 requires the entity to inform its Reliability Coordinator of that inability. The Reliability Coordinator can only build an alternative plan if it is told promptly.

Reference: IRO-001-4 R2, R3

The full bank

The other 34 Next-Day Planning questions

Full Access opens all 36 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 3.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.