3.a · Emergency Preparedness · free sample

Same-Day and Next-Day Planning

3.a Same-Day and Next-Day Planning is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 4 scored questions on RC, 4 on BT, 4 on TO and 4 on BI. It carries the same weight on all four exams. Grid Prep has 36 questions on it. In the bank, they most often cite IRO-017-1, TOP-002-4 and EOP-011-4. 3 are free below.

Free sample: 3 of 36

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

NERC Reliability Standard IRO-014-3 requires each Reliability Coordinator's coordination documents with adjacent Reliability Coordinator Areas to cover the exchange of

  1. A. generator fuel supply contract terms
  2. B. hourly energy billing statements
  3. C. retail customer metering and billing records
  4. D. planned and unplanned outage information
Show the answer

Answer D planned and unplanned outage information

Part 1.4 of Requirement R1 lists the exchange of information including planned and unplanned outage information to support Operational Planning Analyses and Real-time Assessments. The other items are commercial or retail data that have no bearing on an adjacent Reliability Coordinator's studies.

Reference: IRO-014-3 R1 Part 1.4

Question 2 · Analysis

A Reliability Coordinator issues an Operating Instruction to postpone a Transmission outage, but the crew is already inside the equipment and the line cannot be safely returned. What must the Transmission Operator do?

  1. A. Inform its Reliability Coordinator that it cannot perform the instruction
  2. B. Refer the instruction to its Planning Coordinator for a ruling
  3. C. Log the conflict and raise it at the next shift turnover
  4. D. Return the line to service anyway, since the instruction is mandatory
Show the answer

Answer A Inform its Reliability Coordinator that it cannot perform the instruction

Requirement R2 requires compliance with a Reliability Coordinator's Operating Instruction unless it cannot be physically implemented or would violate safety, equipment, regulatory or statutory requirements, and Requirement R3 requires the entity to inform its Reliability Coordinator of that inability. The Reliability Coordinator can only build an alternative plan if it is told promptly.

Reference: IRO-001-4 R2, R3

Question 3 · Application

A Balancing Authority submits its Operating Plan for mitigating Capacity and Energy Emergencies to its Reliability Coordinator. Within what period must the Reliability Coordinator complete its review?

  1. A. 10 calendar days
  2. B. 60 calendar days
  3. C. 30 calendar days
  4. D. 90 calendar days
Show the answer

Answer C 30 calendar days

EOP-011-4 R3 Part 3.1 gives the Reliability Coordinator 30 calendar days from receipt to review the plan for compatibility with the plans of other Balancing Authorities and Transmission Operators, to check it for Wide Area risk, and to notify the submitting entity of the results. The clock runs from each submittal, not from a fixed date in the year, and no other period appears in the requirement.

Reference: EOP-011-4 R3 Part 3.1

The full bank

The other 33 Next-Day Planning questions

Full Access opens all 36 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 3.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.