Grid Prep Start free Buy US$10

2.b · Transmission · free sample

Voltage and Reactive

2.b Voltage and Reactive is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 5 scored questions on RC, 5 on BT, 5 on TO and 2 on BI. On RC, BT and TO that is the most any single area carries. Grid Prep has 45 questions on it. In the bank, they most often cite VAR-001-5, VAR-002-4.1 and MOD-025-2. 3 are free below.

Free sample: 3 of 45

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

A generator's power system stabilizer trips out of service and stays out. VAR-002-4.1 requires the Generator Operator to notify the Transmission Operator within...

  1. A. 30 minutes of the status change
  2. B. 24 hours of the status change
  3. C. 60 minutes of the status change
  4. D. the end of the operating day
Show the answer

Answer A 30 minutes of the status change

R3 sets a 30-minute notification window for a status change on the AVR, the power system stabilizer or an alternative voltage controlling device. The Transmission Operator needs that quickly because the loss changes the reactive support it is counting on in Real-time.

Reference: VAR-002-4.1 R3

Question 2 · Application

An automatic voltage regulator trips at 14:05 and is back in service at 14:22. What does VAR-002-4.1 oblige the Generator Operator to do about that status change?

  1. A. Nothing, as the status returned within 30 minutes
  2. B. Notify the Transmission Operator before 14:35 regardless
  3. C. Report the trip to its Reliability Coordinator today
  4. D. Hold a record for the Transmission Planner's next request
Show the answer

Answer A Nothing, as the status returned within 30 minutes

R3 sets a 30-minute notification window but excuses the notification entirely when the status is restored within 30 minutes of the change, and 14:05 to 14:22 is 17 minutes. Had the regulator stayed out past 14:35, the notification would have been due.

Reference: VAR-002-4.1 R3

Question 3 · Application

A unit's Reactive Power capability verification is metered on the high side of the generator step-up transformer. What must the recorded data account for?

  1. A. The governor droop setting, recorded at the same instant
  2. B. The voltage at the far end of the outgoing transmission line
  3. C. The charging of the outgoing circuits, subtracted from the total
  4. D. The transformer's real and reactive losses, calculated or estimated
Show the answer

Answer D The transformer's real and reactive losses, calculated or estimated

MOD-025-2 Attachment 1 directs that generator step-up transformer losses be calculated when the verification measurements are taken from the high side, and allows them to be estimated from the transformer impedance if necessary; those losses are then reported with the verification data.

Reference: MOD-025-2 R2; Attachment 1, verification specifications 2.4 and 3.7

The full bank

The other 42 Voltage and Reactive questions

Full Access opens all 45 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 2.b holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.