A generator's power system stabilizer trips out of service and stays out. VAR-002-4.1 requires the Generator Operator to notify the Transmission Operator within...
- A. 30 minutes of the status change
- B. 24 hours of the status change
- C. 60 minutes of the status change
- D. the end of the operating day
Show the answer
Answer A 30 minutes of the status change
R3 sets a 30-minute notification window for a status change on the AVR, the power system stabilizer or an alternative voltage controlling device. The Transmission Operator needs that quickly because the loss changes the reactive support it is counting on in Real-time.
Reference: VAR-002-4.1 R3
An automatic voltage regulator trips at 14:05 and is back in service at 14:22. What does VAR-002-4.1 oblige the Generator Operator to do about that status change?
- A. Nothing, as the status returned within 30 minutes
- B. Notify the Transmission Operator before 14:35 regardless
- C. Report the trip to its Reliability Coordinator today
- D. Hold a record for the Transmission Planner's next request
Show the answer
Answer A Nothing, as the status returned within 30 minutes
R3 sets a 30-minute notification window but excuses the notification entirely when the status is restored within 30 minutes of the change, and 14:05 to 14:22 is 17 minutes. Had the regulator stayed out past 14:35, the notification would have been due.
Reference: VAR-002-4.1 R3
A unit's Reactive Power capability verification is metered on the high side of the generator step-up transformer. What must the recorded data account for?
- A. The governor droop setting, recorded at the same instant
- B. The voltage at the far end of the outgoing transmission line
- C. The charging of the outgoing circuits, subtracted from the total
- D. The transformer's real and reactive losses, calculated or estimated
Show the answer
Answer D The transformer's real and reactive losses, calculated or estimated
MOD-025-2 Attachment 1 directs that generator step-up transformer losses be calculated when the verification measurements are taken from the high side, and allows them to be estimated from the transformer impedance if necessary; those losses are then reported with the verification data.
Reference: MOD-025-2 R2; Attachment 1, verification specifications 2.4 and 3.7