Free sample: 3 of 36
Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.
A Generator Operator disagrees with the reporting deadline its Reliability Coordinator has written into the data specification it received. How is that disagreement meant to be settled?
- A. By referring the matter to the Regional Entity for a binding ruling
- B. By withholding the data until the Reliability Coordinator revises the deadline
- C. By using the mutually agreeable process the specification identifies
- D. By applying whichever deadline the Generator Operator's own systems support
Show the answer
Answer C By using the mutually agreeable process the specification identifies
IRO-010-5 R1 Part 1.4 requires the specification itself to identify a mutually agreeable process for resolving conflicts, so that process is the route. Withholding data is not an option, because R3 obliges the receiving entity to satisfy the obligations of the documented specification.
Reference: IRO-010-5 R1 Part 1.4; IRO-010-5 R3
A Transmission Operator realizes that a MW value it sent under its Reliability Coordinator's documented data specification was wrong. Which element of that specification provides for supplying the corrected value?
- A. Performance criteria for the accuracy of data
- B. Provisions to update or correct data and information
- C. Specific deadlines for providing data and information
- D. A mutually agreeable format for the data
Show the answer
Answer B Provisions to update or correct data and information
IRO-010-5 Requirement R1 Part 1.5.3 puts provisions to update or correct data and information into the methods the specification sets for data providers. Deadlines, accuracy criteria and format are separate parts of that same list and none of them covers replacing a value already sent.
Reference: IRO-010-5 R1 Part 1.5.3
A Reliability Coordinator's documented process for the quality of Real-time data must contain which of the following?
- A. Repair deadlines for a failed remote terminal unit
- B. Criteria for evaluating the quality of Real-time data
- C. Inventory of the alarm points in the Control Center
- D. Calibration intervals for telemetered analog points
Show the answer
Answer B Criteria for evaluating the quality of Real-time data
Requirement R1 Part 1.1 of IRO-018-1(i) calls for criteria that let the Reliability Coordinator judge whether Real-time data is good enough to use. The standard sets no calibration interval, no repair deadline and no alarm inventory.
Reference: IRO-018-1(i) R1 Part 1.1