6.a Reporting Requirements is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 3 scored questions on RC, 3 on BT, 3 on TO and 3 on BI. It carries the same weight on all four exams. Grid Prep has 30 questions on it. In the bank, they most often cite EOP-004-4 and TOP-001-6. 3 are free below.

Free sample: 3 of 30

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Analysis

Overnight, thieves strip copper grounding conductors from a fence line at a Generator Owner's switchyard, and normal operation of the switchyard is unaffected. Judged against the damage or destruction of its Facility event type, this incident is:

  1. A. reportable, because the damage came from intentional human action
  2. B. not reportable, because a Generator Owner is outside the standard's scope
  3. C. reportable, because theft of any Bulk Electric System equipment qualifies
  4. D. not reportable, because theft leaving normal operation intact is excluded
Show the answer

Answer D not reportable, because theft leaving normal operation intact is excluded

The damage or destruction of its Facility row covers damage from actual or suspected intentional human action but states that it is not necessary to report theft unless it degrades normal operation of the Facility. Generator Owners are Responsible Entities under EOP-004-4, so applicability is not what decides this.

Reference: EOP-004-4 Attachment 1

Question 2 · Recall

A Generator Operator finds that it cannot physically carry out an Operating Instruction issued by its Reliability Coordinator. What must it do?

  1. A. Notify its Balancing Authority, which relays the refusal
  2. B. File a written explanation with its Regional Entity
  3. C. Inform its Reliability Coordinator that it cannot perform it
  4. D. Carry out the instruction and log the resulting damage
Show the answer

Answer C Inform its Reliability Coordinator that it cannot perform it

IRO-001-4 R3 puts the notification on the entity itself: it informs its Reliability Coordinator of its inability to perform the Operating Instruction. R2 excuses non-compliance only where the instruction cannot be physically implemented or would violate safety, equipment, regulatory or statutory requirements, so carrying it out anyway is not the answer, and routing word through another entity does not satisfy R3.

Reference: IRO-001-4 R2, R3

Question 3 · Application

A Remedial Action Scheme in a Transmission Operator Area has degraded in a way that impacts System reliability. Which document sets out how the Reliability Coordinator is told?

  1. A. The Reliability Coordinator's System Operating Limit methodology
  2. B. The Transmission Operator's next-day Operational Planning Analysis
  3. C. The entity's event reporting Operating Plan for reportable events
  4. D. The Reliability Coordinator's data and information specification
Show the answer

Answer D The Reliability Coordinator's data and information specification

IRO-010-5 R1 Part 1.2 requires the Reliability Coordinator's documented specification to contain provisions for notification of current Protection System and Remedial Action Scheme status or degradation that impacts System reliability. The event reporting Operating Plan covers only the event types listed in EOP-004-4 Attachment 1, which do not include a degraded Remedial Action Scheme.

Reference: IRO-010-5 R1 Part 1.2

The full bank

The other 27 Reporting Requirements questions

Full Access opens all 30 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 6.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.