4.b Response to System Disturbances is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 4 scored questions on RC, 4 on BT, 4 on TO and 3 on BI. Grid Prep has 36 questions on it. In the bank, they most often cite PRC-006-5, PRC-010-2 and PRC-030-1. 3 are free below.

Free sample: 3 of 36

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Application

After a disturbance an analyst needs to establish the order in which breakers and relays operated. Which category of Disturbance Monitoring Equipment gives that order directly?

  1. A. Revenue metering recorders
  2. B. Sequence of event recorders
  3. C. Dynamic Disturbance Recorders
  4. D. Fault recorders
Show the answer

Answer B Sequence of event recorders

The Glossary splits Disturbance Monitoring Equipment into sequence of event recorders, which record equipment response to the event, fault recorders, which capture the waveforms of system voltages and currents, and Dynamic Disturbance Recorders, which capture behavior such as 0.1 Hz to 3 Hz oscillations and abnormal frequency or voltage excursions. Only the first hands the analyst the order of operation.

Reference: NERC Glossary - Disturbance Monitoring Equipment (DME)

Question 2 · Recall

A Planning Coordinator maintains a database that models the Undervoltage Load Shedding (UVLS) Programs in its area. Under PRC-010-2, where does the data in that database come from?

  1. A. From the UVLS entities, in the format the Planning Coordinator specifies
  2. B. From the Regional Entity's compliance filings for each UVLS program
  3. C. From the Reliability Coordinator's System Operating Limit methodology
  4. D. From the Transmission Operator's Real-time state estimator solution
Show the answer

Answer A From the UVLS entities, in the format the Planning Coordinator specifies

PRC-010-2 Requirement R7 has each UVLS entity provide data to its Planning Coordinator according to the format and schedule the Planning Coordinator specifies, which is what keeps the UVLS Program database usable for event analyses. The database is built from the owners of the equipment, not from operating tools or compliance paperwork.

Reference: PRC-010-2 R7; PRC-010-2 R6

Question 3 · Application

NERC Reliability Standard PRC-024-4 requires generator frequency protection to be set so that it will not trip inside a defined no trip zone. During a frequency excursion, what does that setting achieve?

  1. A. Underfrequency relays on load circuits are blocked temporarily
  2. B. Generating resources trip before load shedding relays operate
  3. C. Generating resources stay connected while frequency recovers
  4. D. Governor response is boosted while the excursion lasts
Show the answer

Answer C Generating resources stay connected while frequency recovers

Requirement R1 requires frequency protection to be set so the generating resource does not trip within the no trip zone of PRC-024 Attachment 1. Holding machines on line through the excursion is what gives governor response and underfrequency load shedding time to arrest the decline.

Reference: PRC-024-4 R1

The full bank

The other 33 System Disturbances questions

Full Access opens all 36 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 4.b holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.