A Transmission Operator adds new alarm points and new displays to the energy management system at its primary control center. Which part of its Operating Plan for backup functionality governs what happens next?
- A. The Operating Procedure for deciding when to move to backup
- B. The annual test demonstrating two continuous hours of backup use
- C. The list of entities notified when operating locations change
- D. The Operating Process keeping backup and primary consistent
Show the answer
Answer D The Operating Process keeping backup and primary consistent
R1 Part 1.3 requires an Operating Process for keeping the backup functionality consistent with the primary control center, which is what a change to primary displays and alarms triggers. The decision-authority procedure, the notification list and the annual test all deal with using or proving the backup, not with maintaining it in step.
Reference: EOP-008-2 R1 Part 1.3
A Reliability Coordinator's monthly test of its Alternative Interpersonal Communication capability comes back unsuccessful. What is required next?
- A. A replacement must be designated before the next monthly test
- B. Repair or replacement must be initiated within two hours
- C. The capability must be fully restored within two hours
- D. Its Regional Entity must be told within 24 hours of the test
Show the answer
Answer B Repair or replacement must be initiated within two hours
After an unsuccessful test the entity has 2 hours to initiate action to repair the capability or to designate a replacement. The trap is full restoration in two hours: the obligation is to start the repair or name a substitute, not to have the link working again by then.
Reference: COM-001-3 R9
During a planned cutover to its backup control center, a Balancing Authority's telemetry to its Reliability Coordinator will be out for about twenty minutes. What should the operator do?
- A. Log the outage only, since telemetry is not a monitoring capability
- B. Notify the Reliability Coordinator, since all planned outages count
- C. Skip the notification, since the outage is under thirty minutes
- D. Notify the Regional Entity instead, since the outage is planned
Show the answer
Answer B Notify the Reliability Coordinator, since all planned outages count
The thirty-minute threshold applies only to unplanned outages. All planned outages of telemetering and control equipment, monitoring and assessment capabilities, and the associated communication channels are notified to the Reliability Coordinator and known impacted interconnected entities whatever their length.
Reference: TOP-001-6 R9