A Reliability Coordinator's tools have marked a group of Real-time measurements suspect. How must that be made known to the System Operator on shift?
- A. Through a monthly data quality report to the Regional Entity
- B. Through a quality flag or color code on the display
- C. Through a daily summary sent by the modeling group
- D. Through a note in the next shift turnover log
Show the answer
Answer B Through a quality flag or color code on the display
IRO-018-1(i) Requirement R1 Part 1.2 requires provisions to indicate the quality of Real-time data to the System Operator, and the supplemental material offers display color codes and data quality flags as examples. A summary or report after the fact does not help the operator judge the assessment in front of them.
Reference: IRO-018-1(i) R1.2
A state estimator solution shows a real-power mismatch of 350 MW on a model carrying 42,000 MW of Load. As a share of modeled Load, that mismatch is closest to:
- A. 1.2 percent
- B. 0.4 percent
- C. 0.8 percent
- D. 8.3 percent
Show the answer
Answer C 0.8 percent
350 divided by 42,000 is 0.00833, or about 0.8 percent. Reading it as 8.3 percent misplaces the decimal by a factor of ten, which would mean a mismatch of 3,500 MW.
Reference: Power system fundamentals
Telemetering equipment feeding a Transmission Operator's State Estimator will be taken out of service for 45 minutes of planned maintenance. What does NERC Reliability Standard TOP-001-6 require?
- A. Notify its Reliability Coordinator and known impacted entities
- B. Notify NERC and the Regional Entity before the work begins
- C. Shift the affected points to manual entry and log the change
- D. Complete a Real-time Assessment before the equipment is removed
Show the answer
Answer A Notify its Reliability Coordinator and known impacted entities
Requirement R9 requires each Balancing Authority and Transmission Operator to notify its Reliability Coordinator and known impacted interconnected entities of all planned outages, and unplanned outages of 30 minutes or more, of telemetering and control equipment, monitoring and assessment capabilities and the associated communication channels. The 30-minute threshold applies only to unplanned outages, so this planned work is reportable regardless of its length.
Reference: TOP-001-6 R9