Grid Prep Start free Buy US$10

5.a · Contingency Analysis and Reliability · free sample

Contingency Analysis

5.a Contingency Analysis is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 5 scored questions on RC, 4 on BT, 4 on TO and 2 on BI. On RC that is the most any single area carries. Grid Prep has 45 questions on it. In the bank, they most often cite FAC-011-4 and TOP-001-6. 3 are free below.

Free sample: 3 of 45

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

A steady-state contingency analysis run checks flows and voltages. How may a Reliability Coordinator assess instability, Cascading and uncontrolled separation for the Contingencies it studies?

  1. A. By predetermined stability limits or offline analysis
  2. B. By the same steady-state run that checks the flows
  3. C. By the Undervoltage Load Shedding Program's settings
  4. D. By the state estimator's bad-data and residual checks
Show the answer

Answer A By predetermined stability limits or offline analysis

FAC-011-4 states that assessments of instability, Cascading and uncontrolled separation may be performed with real-time stability assessments, predetermined stability limits or other offline analysis techniques. A steady-state solution reports flows and voltages only, and the methodology is barred from leaning on Undervoltage Load Shedding Programs when stability limits are established.

Reference: FAC-011-4 R6, footnote 1; R4, Part 4.7

Question 2 · Application

A bus sits at 0.97 per unit before the Contingency and at 0.91 per unit after it, against an emergency low limit of 0.92 per unit. How deep is the exceedance?

  1. A. 0.01 per unit below the emergency limit
  2. B. 0.05 per unit below the emergency limit
  3. C. 0.06 per unit below the emergency limit
  4. D. 0.01 per unit above the emergency limit
Show the answer

Answer A 0.01 per unit below the emergency limit

The post-Contingency voltage is what the emergency limit is tested against: 0.92 - 0.91 = 0.01 per unit below the limit. The 0.06 per unit figure is the drop from the pre-Contingency voltage and 0.05 per unit is the pre-Contingency margin, and neither is the exceedance.

Reference: FAC-011-4 R6, Part 6.2.2; power system fundamentals

Question 3 · Application

Contingency analysis identifies an exceedance that could lead to uncontrolled separation across the Interconnection. Which limit is being exceeded?

  1. A. An Interconnection Reliability Operating Limit
  2. B. A normal System Voltage Limit at one bus
  3. C. A Facility Rating on a single station transformer
  4. D. An hourly Contingency Reserve obligation
Show the answer

Answer A An Interconnection Reliability Operating Limit

The Glossary defines an Interconnection Reliability Operating Limit as a System Operating Limit that, if violated, could lead to instability, uncontrolled separation, or Cascading outages that adversely impact Bulk Electric System reliability. FAC-011-4 R8 requires the Reliability Coordinator's methodology to describe how the subset of SOLs qualifying as IROLs is identified.

Reference: NERC Glossary - Interconnection Reliability Operating Limit; FAC-011-4 R8

The full bank

The other 42 Contingency Analysis questions

Full Access opens all 45 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 5.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.