Grid Prep Start free

5.a · Contingency Analysis and Reliability · free sample

Contingency Analysis

5.a Contingency Analysis is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 5 scored questions on RC, 4 on BT, 4 on TO and 2 on BI. On RC that is the most any single area carries. Grid Prep has 45 questions on it. In the bank, they most often cite FAC-011-4 and TOP-001-6. Two are free below.

Free sample: 2 of 45

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

A steady-state contingency analysis run checks flows and voltages. How may a Reliability Coordinator assess instability, Cascading and uncontrolled separation for the Contingencies it studies?

  1. A. By predetermined stability limits or offline analysis
  2. B. By the same steady-state run that checks the flows
  3. C. By the state estimator's bad-data and residual checks
  4. D. By the Undervoltage Load Shedding Program's settings
Show the answer

Answer A By predetermined stability limits or offline analysis

FAC-011-4 states that assessments of instability, Cascading and uncontrolled separation may be performed with real-time stability assessments, predetermined stability limits or other offline analysis techniques. A steady-state solution reports flows and voltages only, and the methodology is barred from leaning on Undervoltage Load Shedding Programs when stability limits are established.

Reference: FAC-011-4 R6, footnote 1; R4, Part 4.7

Question 2 · Application

A bus sits at 0.97 per unit before the Contingency and at 0.91 per unit after it, against an emergency low limit of 0.92 per unit. How deep is the exceedance?

  1. A. 0.06 per unit below the emergency limit
  2. B. 0.01 per unit below the emergency limit
  3. C. 0.05 per unit below the emergency limit
  4. D. 0.01 per unit above the emergency limit
Show the answer

Answer B 0.01 per unit below the emergency limit

The post-Contingency voltage is what the emergency limit is tested against: 0.92 - 0.91 = 0.01 per unit below the limit. The 0.06 per unit figure is the drop from the pre-Contingency voltage and 0.05 per unit is the pre-Contingency margin, and neither is the exceedance.

Reference: FAC-011-4 R6, Part 6.2.2; power system fundamentals

The full bank

The other 43 Contingency Analysis questions

Full Access opens all 45 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 5.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.