A Transmission Loading Relief (TLR) Log must be filed after any TLR event at or above which level?
- A. Level 5
- B. Level 1
- C. Level 3
- D. Level 2
Show the answer
Answer D Level 2
The NERC Glossary defines the TLR Log as the report required after every TLR Level 2 or higher. The NERC Interchange Distribution Calculator prepares it, the issuing Reliability Coordinator reviews and approves it, and it is then filed in a public area of the NERC web site.
Reference: NERC Glossary - TLR (Transmission Loading Relief) Log
A generator sited in Balancing Authority M is moved by Dynamic Transfer into the effective control boundaries of Balancing Authority N. Balancing Authority N is therefore the
- A. Sending Balancing Authority
- B. Intermediate Balancing Authority
- C. Native Balancing Authority
- D. Attaining Balancing Authority
Show the answer
Answer D Attaining Balancing Authority
The NERC Glossary defines the Attaining Balancing Authority as the one bringing generation or load into its effective control boundaries through a Dynamic Transfer, which is Balancing Authority N here. Balancing Authority M, which gives the resource up from its boundaries, is the Native Balancing Authority, and an Intermediate Balancing Authority is a different idea again: one sitting on the scheduling path of an Interchange Transaction.
Reference: NERC Glossary - Attaining Balancing Authority; Native Balancing Authority; Dynamic Transfer
While assessing an Arranged Interchange, a Source Balancing Authority concludes that it cannot support the requested magnitude, including ramping, for the whole duration. What must it do?
- A. Deny the Arranged Interchange within the response window
- B. Approve it and ask the Sink Balancing Authority for a slower ramp
- C. Refer the decision to its Reliability Coordinator for approval
- D. Approve it and lower its own generation to compensate
Show the answer
Answer A Deny the Arranged Interchange within the response window
Requirement R1 Part 1.1 makes denial mandatory for a Source or Sink Balancing Authority that does not expect to support the magnitude of the Interchange, ramping included, throughout its duration. Renegotiating the ramp with the counterparty is not an alternative the standard offers.
Reference: INT-006-5 R1.1