Grid Prep Start free Buy US$10

1.a · Resource and Demand Balancing · free sample

Interchange Scheduling and Coordination

1.a Interchange Scheduling and Coordination is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 3 scored questions on RC, 4 on BT, 1 on TO and 5 on BI. On BI that is the most any single area carries. On TO it is a single question. Grid Prep has 45 questions on it. In the bank, they most often cite INT-006-5, INT-009-3 and IRO-006-5. 3 are free below.

Free sample: 3 of 45

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

A Transmission Loading Relief (TLR) Log must be filed after any TLR event at or above which level?

  1. A. Level 5
  2. B. Level 1
  3. C. Level 3
  4. D. Level 2
Show the answer

Answer D Level 2

The NERC Glossary defines the TLR Log as the report required after every TLR Level 2 or higher. The NERC Interchange Distribution Calculator prepares it, the issuing Reliability Coordinator reviews and approves it, and it is then filed in a public area of the NERC web site.

Reference: NERC Glossary - TLR (Transmission Loading Relief) Log

Question 2 · Application

A generator sited in Balancing Authority M is moved by Dynamic Transfer into the effective control boundaries of Balancing Authority N. Balancing Authority N is therefore the

  1. A. Sending Balancing Authority
  2. B. Intermediate Balancing Authority
  3. C. Native Balancing Authority
  4. D. Attaining Balancing Authority
Show the answer

Answer D Attaining Balancing Authority

The NERC Glossary defines the Attaining Balancing Authority as the one bringing generation or load into its effective control boundaries through a Dynamic Transfer, which is Balancing Authority N here. Balancing Authority M, which gives the resource up from its boundaries, is the Native Balancing Authority, and an Intermediate Balancing Authority is a different idea again: one sitting on the scheduling path of an Interchange Transaction.

Reference: NERC Glossary - Attaining Balancing Authority; Native Balancing Authority; Dynamic Transfer

Question 3 · Analysis

While assessing an Arranged Interchange, a Source Balancing Authority concludes that it cannot support the requested magnitude, including ramping, for the whole duration. What must it do?

  1. A. Deny the Arranged Interchange within the response window
  2. B. Approve it and ask the Sink Balancing Authority for a slower ramp
  3. C. Refer the decision to its Reliability Coordinator for approval
  4. D. Approve it and lower its own generation to compensate
Show the answer

Answer A Deny the Arranged Interchange within the response window

Requirement R1 Part 1.1 makes denial mandatory for a Source or Sink Balancing Authority that does not expect to support the magnitude of the Interchange, ramping included, throughout its duration. Renegotiating the ramp with the counterparty is not an alternative the standard offers.

Reference: INT-006-5 R1.1

The full bank

The other 42 Interchange Scheduling questions

Full Access opens all 45 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 1.a holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.