Grid Prep Start free Buy US$10

1.f · Resource and Demand Balancing · free sample

Load Forecasting

1.f Load Forecasting is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 3 scored questions on RC, 3 on BT, 2 on TO and 4 on BI. Grid Prep has 36 questions on it. In the bank, they most often cite EOP-011-4 and TOP-002-4. 3 are free below.

Free sample: 3 of 36

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Application

Across four hours a forecast read 10,200 / 10,000 / 10,100 / 9,700 MW against actuals of 10,000 / 10,200 / 9,800 / 10,000 MW. Its mean error and mean absolute error are

  1. A. 250 MW and 250 MW
  2. B. 125 MW and 500 MW
  3. C. 0 MW and 250 MW
  4. D. 0 MW and 0 MW
Show the answer

Answer C 0 MW and 250 MW

The signed errors, forecast minus actual, are +200, -200, +300 and -300 MW, which sum to zero, so the mean error - the bias - is 0 MW. The absolute errors are 200, 200, 300 and 300 MW and average 250 MW, so this forecast is unbiased but far from precise.

Reference: Load forecasting practice - forecast error and bias

Question 2 · Recall

The NERC Glossary describes Operating Reserve as capability above firm system demand held for regulation, equipment forced and scheduled outages, local area protection, and

  1. A. transmission losses
  2. B. load forecasting error
  3. C. voltage schedule support
  4. D. frequency bias settings
Show the answer

Answer B load forecasting error

Operating Reserve exists partly to cover the gap between forecast and actual Demand, which is why load forecasting error sits in the definition beside regulation, outages and local area protection. Losses, voltage support and frequency bias are handled by other means and are no part of the term.

Reference: NERC Glossary - Operating Reserve

Question 3 · Analysis

Demand across a Reliability Coordinator Area is climbing well above forecast, and the latest Real-time Assessment shows an expected System Operating Limit exceedance on a transfer path. What must the Reliability Coordinator do?

  1. A. Notify the Generator Operators on the path and revise the limit upward
  2. B. Notify the impacted Transmission Operators only after the limit has actually been exceeded
  3. C. Notify impacted Transmission Operators, Balancing Authorities and Reliability Coordinators
  4. D. Notify its Regional Entity and file an exceedance report within twenty-four hours
Show the answer

Answer C Notify impacted Transmission Operators, Balancing Authorities and Reliability Coordinators

IRO-008-3 R5 is triggered by an actual or expected condition, so the notification goes out ahead of the exceedance, in accordance with the SOL methodology, to impacted Transmission Operators and Balancing Authorities in the Area and to other impacted Reliability Coordinators. R6 then calls for a second notification once the exceedance has been prevented or mitigated.

Reference: IRO-008-3 R5

The full bank

The other 33 Load Forecasting questions

Full Access opens all 36 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 1.f holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.