Grid Prep Start free Buy US$10

1.e · Resource and Demand Balancing · free sample

Frequency

1.e Frequency is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 4 scored questions on RC, 5 on BT, 3 on TO and 5 on BI. On BT and BI that is the most any single area carries. Grid Prep has 45 questions on it. In the bank, they most often cite BAL-003-2, PRC-006-5 and PRC-024-4. 3 are free below.

Free sample: 3 of 45

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Recall

PRC-024-4 applies to the frequency protection on several parts of a generating Facility. Which protection does the standard expressly exempt?

  1. A. Protection on individual dispersed type 1 or type 2 wind resources
  2. B. Protection on the generator step-up transformer of a BES resource
  3. C. Protection on auxiliary equipment within the generating Facility
  4. D. Protection on the high side of a unit auxiliary transformer
Show the answer

Answer C Protection on auxiliary equipment within the generating Facility

Facilities Section 4.2.3 exempts protection on all auxiliary equipment within the synchronous generator, type 1 or type 2 wind resource, or synchronous condenser Facility. The generator step-up transformer, the high side of a generator-connected unit auxiliary transformer and individual dispersed type 1 or type 2 wind resources all sit inside the standard's scope under Section 4.2.1.

Reference: PRC-024-4 Applicability 4.2.1 and 4.2.3

Question 2 · Application

The Underfrequency Performance Characteristic in PRC-006-5 Attachment 1 is f = 0.575 log(t) + 57.83 Hz for times between 2 and 60 seconds. Where does that boundary sit 20 seconds into a simulation?

  1. A. 58.00 Hz
  2. B. 58.38 Hz
  3. C. 59.30 Hz
  4. D. 58.58 Hz
Show the answer

Answer D 58.58 Hz

The log of 20 is 1.301, and 0.575 x 1.301 = 0.748, so the curve sits at 57.83 + 0.75 = 58.58 Hz at 20 seconds, and simulated frequency must stay above it. The 58.38 Hz value comes from the Generator Underfrequency Trip Modeling curve, which uses 57.63 in place of 57.83.

Reference: PRC-006-5 Attachment 1

Question 3 · Recall

NERC Reliability Standard PRC-024-4 requires a Generator Owner to set the frequency protection on an applicable generating resource so that it

  1. A. trips the resource as soon as frequency leaves the no trip zone
  2. B. allows the resource to ride through the whole no trip zone
  3. C. follows the load shedding steps set by the Planning Coordinator
  4. D. opens the unit breaker before volts per hertz reaches 1.18 per unit
Show the answer

Answer B allows the resource to ride through the whole no trip zone

Requirement R1 calls for frequency protection set in accordance with Attachment 1 so that it does not cause the resource to trip inside the no trip zone; only documented regulatory or equipment limitations are excepted. The standard also states that the area outside the zone is not a must trip zone.

Reference: PRC-024-4 R1; PRC-024-4 Attachment 1

The full bank

The other 42 Frequency questions

Full Access opens all 45 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 1.e holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.