1.h Energy Sources (e.g., hydroelectric, solar, thermal) is one of the 31 knowledge areas in the NERC System Operator Certification content outlines. It is worth 2 scored questions on RC, 3 on BT, 2 on TO and 3 on BI. Grid Prep has 30 questions on it. In the bank, they most often cite PRC-029-2 and PRC-024-4. 3 are free below.

Free sample: 3 of 30

Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.

Question 1 · Application

Eastern Interconnection frequency settles at 59.6 Hz for two minutes after a large generation loss. Under NERC Reliability Standard PRC-024-4 Attachment 1, applicable frequency protection must

  1. A. trip the resource once the excursion has lasted more than 180 seconds
  2. B. let the resource keep operating, since 59.6 Hz is above 59.5 Hz
  3. C. trip the resource instantaneously, as 59.6 Hz is below 60.0 Hz
  4. D. allow ten seconds of operation and then trip the resource
Show the answer

Answer B let the resource keep operating, since 59.6 Hz is above 59.5 Hz

Table 1 of Attachment 1 places the Eastern Interconnection continuous-operation boundary above 59.5 Hz, so at 59.6 Hz the protection must not trip the resource, no matter how long the excursion lasts. The 180-second figure comes from the Western Interconnection table, at 59.4 Hz and below.

Reference: PRC-024-4 R1 and Attachment 1, Table 1

Question 2 · Recall

In the NERC Glossary of Terms, the defined term Curtailment refers specifically to...

  1. A. a cut in the transfer capability of a constrained transmission path
  2. B. a cut in Firm Demand served while an Energy Emergency is declared
  3. C. a cut in the scheduled capacity or energy of an Interchange Transaction
  4. D. a cut in a wind or solar plant's output ordered by the dispatcher
Show the answer

Answer C a cut in the scheduled capacity or energy of an Interchange Transaction

NERC's definition is narrow: it is a reduction in the scheduled capacity or energy delivery of an Interchange Transaction. Backing a wind or solar plant down is a dispatch action operators also call curtailment in conversation, but it is not what the defined term covers.

Reference: NERC Glossary - Curtailment

Question 3 · Application

Wind turbine output varies with the cube of wind speed below rated wind speed. If the wind at a plant rises 10% while it is still below rated, available Real Power rises by...

  1. A. about 21%
  2. B. about 33%
  3. C. about 10%
  4. D. about 66%
Show the answer

Answer B about 33%

Power in the wind goes as the cube of speed, so 1.10 cubed is 1.331, about a 33% increase. Squaring instead of cubing gives 21%, and treating the relationship as linear gives 10%.

Reference: Power system fundamentals

The full bank

The other 27 Energy Sources questions

Full Access opens all 30 in this area as 12-question sets, least-seen first, plus the rest of the 1,224 and unlimited mock exams at exam pace. The Library card for 1.h holds the area's seven must-know numbers. To start free in the browser: 50 practice answers and a 30-question timed taster, split to your exam's weighting.

In the iPhone, iPad and Mac app the Library is free, and Full Access is a one-time in-app purchase.