Answer each one before you open the explanation. On the exam there's no explanation, and you have about 77 seconds a question on RC and BT, 90 on TO and BI.
Which record must a Responsible Entity complete for every Reportable Balancing Contingency Event?
- A. An hourly Energy Emergency Alert update log
- B. A Corrective Action Plan sent to the Regional Entity
- C. CR Form 1, with the date and time of occurrence
- D. FRS Form 1, submitted annually to the ERO
Show the answer
Answer C CR Form 1, with the date and time of occurrence
BAL-002-3 R1 part 1.2 requires every Reportable Balancing Contingency Event to be documented on CR Form 1, and the measure calls for the date and time of occurrence. FRS Form 1 belongs to the annual Frequency Response reporting in BAL-003-2, not to event recovery.
Reference: BAL-002-3 R1 part 1.2 and M1
Recovery for a Reserve Sharing Group is judged on Reserve Sharing Group Reporting ACE. How is that value formed at any time of measurement?
- A. The algebraic sum of its member Balancing Authorities' Reporting ACEs
- B. The most negative Reporting ACE among its member Balancing Authorities
- C. The Reporting ACE of the member Balancing Authority that lost the unit
- D. The hourly average of its member Balancing Authorities' Reporting ACEs
Show the answer
Answer A The algebraic sum of its member Balancing Authorities' Reporting ACEs
The NERC Glossary defines Reserve Sharing Group Reporting ACE as the algebraic sum of the Reporting ACEs of the Balancing Authorities participating in the group at that time of measurement. Because the sum is algebraic, a member running positive offsets a member running negative rather than being set aside.
Reference: NERC Glossary - Reserve Sharing Group Reporting ACE
The Most Severe Single Contingency is the Balancing Contingency Event producing the greatest MW loss of resource output used to meet which obligations?
- A. Firm Demand and export obligation
- B. Firm Demand and Regulating Reserve
- C. Native Load and Contingency Reserve
- D. Total Demand and Interchange schedules
Show the answer
Answer A Firm Demand and export obligation
The definition measures the greatest loss of resource output used to meet Firm Demand and export obligation. Reserve products are what the Most Severe Single Contingency sizes, not part of the load it is measured against.
Reference: NERC Glossary - Most Severe Single Contingency