What minimum accuracy does BAL-005-1 demand of the frequency metering equipment used to calculate Reporting ACE?
- A. 0.0001 Hz
- B. 0.001 Hz
- C. 0.100 Hz
- D. 0.010 Hz
Show the answer
Answer B 0.001 Hz
Requirement R3 Part 3.2 sets the minimum accuracy at 0.001 Hz, and Part 3.1 sets a minimum availability of 99.95 percent for each calendar year. Coarser metering would corrupt the 10B frequency term in Reporting ACE.
Reference: BAL-005-1 R3 Part 3.2
BAL-005-1 sets a minimum yearly availability for the system a Balancing Authority uses to calculate Reporting ACE. Across an 8,760-hour year, what is the longest total unavailability that still meets it?
- A. 87.6 hours
- B. 17.5 hours
- C. 4.4 hours
- D. 43.8 hours
Show the answer
Answer D 43.8 hours
Requirement R5 sets the minimum at 99.5 percent of each calendar year, and 0.5 percent of 8,760 hours is 43.8 hours. The 4.4-hour figure follows from the 99.95 percent availability R3 sets for frequency metering equipment, which is a separate requirement.
Reference: BAL-005-1 R5
A generator sitting inside one Balancing Authority Area is carried as a Pseudo-Tie by a second Balancing Authority. Where does the Pseudo-Tie value land in that second Balancing Authority's Reporting ACE?
- A. In the frequency bias term, scaled by the Frequency Bias Setting
- B. In the Interchange Meter Error term, until the hour is settled
- C. In Actual Net Interchange, the same way a Tie Line does
- D. In Scheduled Net Interchange, the same way an Interchange Schedule does
Show the answer
Answer C In Actual Net Interchange, the same way a Tie Line does
The Glossary defines a Pseudo-Tie as a time-varying energy transfer updated in Real-time and included in the Actual Net Interchange term the same way a Tie Line is. A Dynamic Schedule is the counterpart that lands in Scheduled Net Interchange, which is why the two are so easily confused.
Reference: NERC Glossary - Pseudo-Tie, Dynamic Interchange Schedule